How Long Does a Kitchen Renovation Take in Melbourne?

Updated July 2026

“How long will the kitchen renovation take?” sounds like a straightforward question, but it can refer to two different timelines:

  1. The complete period from initial planning to final handover

  2. The time your existing kitchen is physically unusable

Those periods are not the same.

A properly planned full kitchen renovation will commonly require approximately five to nine weeks of on-site work. The complete process from initial planning, selections and cabinetry production through to handover will more realistically span three to six months.

A simple same-layout replacement may be faster. Structural changes, custom joinery, connected laundry work, flooring or major service upgrades can extend the construction period beyond nine weeks.

These are broad planning ranges—not fixed promises. The scope and procurement strategy determine the real programme.

Typical Kitchen-Renovation Timelines

Cosmetic or straightforward replacement

On-site work: approximately three to five weeks

This may apply when:

  • The existing layout remains

  • Plumbing and electrical locations require minimal alteration

  • There are no structural changes

  • Cabinetry and appliances are confirmed before demolition

  • Benchtop and splashback lead times are controlled

  • Flooring and surrounding rooms remain substantially unchanged

Even this timeline assumes the planning and ordering have happened before the old kitchen is removed.

Complete custom kitchen renovation

On-site work: approximately five to nine weeks

This commonly includes:

  • Demolition and disposal

  • Plumbing and electrical alterations

  • Wall, ceiling and floor preparation

  • Custom cabinetry

  • Templated benchtops

  • Splashback or tiling

  • Appliance installation

  • Painting, finishing and final fit-off

This is a more realistic range for an established Melbourne home where the project goes beyond replacing cabinets in the same positions.

Kitchen with structural or connected work

On-site work: approximately eight to twelve weeks or more

This may apply when the renovation includes:

  • Removing or altering walls

  • Structural engineering

  • New windows or doors

  • Significant plumbing or electrical upgrades

  • Kitchen and laundry cabinetry

  • New flooring through connected rooms

  • Pantry or living-area alterations

  • Ceiling, lighting or heating changes

  • Extensive rectification after demolition

The kitchen may be only one part of the construction sequence.

Phase 1: Brief, Site Review and Feasibility

Typical allowance: one to three weeks

The first phase establishes:

  • What is not working in the existing kitchen

  • What the household wants to improve

  • Appliance requirements

  • Storage needs

  • Layout possibilities

  • Connected laundry, pantry, flooring or lighting work

  • Initial budget expectations

  • Obvious property constraints

This is where unrealistic combinations of scope, budget and timing should be identified—not after the kitchen has been demolished.

Phase 2: Layout and Renovation Planning

Typical allowance: two to six weeks

The layout needs to resolve more than cabinetry appearance. It should account for:

  • Walkways and clearances

  • Appliance dimensions and door openings

  • Preparation and cooking zones

  • Pantry and storage

  • Plumbing and electrical requirements

  • Waste and recycling

  • Benchtop areas

  • Lighting

  • Adjacent rooms and finishes

  • Structural or approval requirements

Several layout options may need to be compared before the project direction becomes clear.

Homeowners who begin ordering appliances or cabinetry before resolving this phase often create expensive compromises later.

Phase 3: Selections, Documentation and Pricing

Typical allowance: two to six weeks

Before construction pricing can become meaningful, the project should identify:

  • Cabinetry finish and internal hardware

  • Benchtop material

  • Sink and tapware

  • Appliances

  • Splashback or wall finish

  • Flooring

  • Lighting and electrical requirements

  • Painting

  • Handles and accessories

  • Work in connected rooms

Unselected items usually become allowances or provisional sums. Those may be necessary in some circumstances, but too many allowances make the final cost and timeline less reliable.

Phase 4: Approvals and Engineering

Typical allowance: project-dependent

A straightforward internal kitchen replacement may not require a building permit. Structural alterations, new openings or other significant work can trigger engineering, surveying or approval requirements.

Apartments may also require owners-corporation approval, contractor documentation, delivery bookings, lift protection and restricted working hours.

These requirements should be investigated before a construction date is promised.

Phase 5: Cabinetry and Long-Lead Procurement

Typical allowance: four to ten weeks or more

Custom cabinetry should generally be manufactured or firmly programmed before demolition begins.

The programme may also depend on:

  • Appliance availability

  • Sink and tapware delivery

  • Cabinet hardware

  • Benchtop slabs

  • Tiles or splashback material

  • Lighting

  • Flooring

  • Custom glass or metalwork

A renovation is not genuinely ready to start because the design looks finished on a screen. The items controlling construction must be ordered, confirmed and coordinated.

Phase 6: Site Protection and Demolition

Typical allowance: two to five working days

This stage can include:

  • Protecting floors and circulation areas

  • Disconnecting plumbing and electrical items

  • Removing existing cabinetry and appliances

  • Demolition and waste disposal

  • Opening walls where required

  • Inspecting previously concealed construction

Demolition can reveal:

  • Water damage

  • Rotten timber

  • Unsafe wiring

  • Outdated plumbing

  • Uneven floors or walls

  • Previous unauthorised alterations

  • Structural conditions that differ from assumptions

A realistic programme should contain a process for assessing and responding to those conditions.

Phase 7: Rough-In and Building Preparation

Typical allowance: one to two weeks

Before cabinetry can be installed, the room may require:

  • Plumbing rough-in

  • Electrical rough-in

  • Structural work

  • Framing and carpentry

  • Wall and ceiling repairs

  • Plastering

  • Floor preparation

  • Window or door alterations

  • Initial painting

Each service must match the approved cabinetry and appliance documentation. Moving outlets or plumbing after cabinetry arrives creates delay and rework.

Phase 8: Cabinet Installation

Typical allowance: three to seven working days

Cabinetry installation timing depends on:

  • Kitchen size

  • Joinery complexity

  • Tall cabinets and integrated appliances

  • Pantry cabinetry

  • Scribed panels

  • Curved or custom details

  • Connected laundry or living-room joinery

  • Site access

After installation, the cabinetry must be checked and prepared for final benchtop measurement where required.

Phase 9: Benchtop Measurement and Installation

Typical allowance: one to three weeks

Many stone, porcelain and similar benchtops are finally measured after the base cabinetry has been installed and checked.

The fabricator then confirms dimensions, cuts the material and returns for installation. This creates an unavoidable gap in the programme unless another benchtop system has been selected.

During this period, the kitchen may look close to completion but remain unusable.

Benchtop lead times should be confirmed before demolition—not discovered after the cabinets are installed.

Phase 10: Splashback, Painting and Finishes

Typical allowance: three to ten working days

After the benchtop is installed, the remaining wall finishes can be completed.

This may include:

  • Tiled splashback

  • Glass or slab splashback

  • Final painting

  • Silicone and sealing

  • Cabinet adjustments

  • Handles and accessories

  • Flooring transitions

Some materials require templating or fabrication after the benchtop, adding another lead time.

Phase 11: Plumbing, Electrical and Appliance Fit-Off

Typical allowance: two to five working days

Final fit-off may include:

  • Sink and tapware

  • Dishwasher

  • Cooktop and oven

  • Rangehood

  • Refrigerator connection

  • Lighting

  • Power points

  • Final plumbing and electrical testing

Appliances must be on site and match the cabinetry and services prepared for them.

Phase 12: Completion and Handove

Typical allowance: two to five working days

The final stage includes:

  • Cleaning

  • Cabinet adjustments

  • Defect checks

  • Testing appliances and services

  • Compliance documentation

  • Explaining care and maintenance

  • Addressing agreed completion items

A kitchen is not complete simply because the cabinets and benchtop are visible.

What Usually Delays a Kitchen Renovation?

Starting before the design is resolved

Demolition should not be used as a substitute for planning. Beginning early can create longer periods without a kitchen and more costly decisions under pressure.

Ordering cabinetry before confirming appliances

Appliance dimensions, ventilation requirements and door clearances directly affect cabinetry.

Changing the layout during construction

Moving a sink, appliance or wall after rough-in affects multiple trades and can invalidate completed work.

Unconfirmed benchtop lead times

Templated benchtops can become the programme’s critical path.

Concealed condition

Existing-home renovations contain uncertainty. The programme should allow the team to inspect and respond rather than conceal or ignore problems.

Separate owner-arranged trades

Owner-supplied trades may be perfectly competent, but unclear responsibility and scheduling can create gaps between work stages.

Apartment and access restrictions

Lift bookings, parking, delivery hours, protection requirements and owners-corporation approvals can affect every stage.

Expanding the scope after work begins

Once the kitchen is open, homeowners often decide to continue flooring, painting or lighting into adjacent rooms. This may produce a better final result but changes the original programme.

How to Reduce the Time Without Cutting Corners

The safest way to shorten construction is to complete more decisions before demolition.

Before the start date:

  • Approve the layout

  • Confirm the complete scope

  • Select appliances

  • Finalise cabinetry

  • Select the benchtop and splashback

  • Confirm flooring and lighting

  • Order long-lead items

  • Resolve approvals

  • Confirm trade sequencing

  • Plan for concealed conditions

  • Establish where the household will prepare food

Trying to accelerate waterproofing, curing, fabrication or required trade work is not smart scheduling. It is simply transferring risk into the finished renovation.

How Long Will You Be Without a Kitchen?

For a complete custom renovation, plan for approximately five to nine weeks without a fully operational kitchen.

You may regain limited functions progressively, but the sink, benchtop, cooktop and appliances will not necessarily become usable at the same time.

Before demolition, arrange:

  • A temporary food-preparation area

  • Refrigerator access

  • Microwave, air fryer or portable cooking where safely appropriate

  • Kettle and basic utensils

  • Disposable or easily washed items

  • A safe washing-up arrangement

  • Protection from dust and construction traffic

Read our guide to living at home during a renovation.

What Should the Contract and Programme Show?

For qualifying major domestic building work, the contract should clearly identify the agreed scope, price, start and completion arrangements and appropriate delay allowances. Consumer Affairs Victoria provides guidance on preparing major domestic building contracts.

Before signing, ask:

  • What does the quoted duration include?

  • When will the kitchen become unusable?

  • Has cabinetry production been included?

  • When will the benchtop be measured and installed?

  • Which products control the programme?

  • Are approvals required?

  • How are concealed conditions handled?

  • Who coordinates each trade?

  • What work will remain at practical completion?

  • How will delays and variations be communicated?

A four-week “installation time” means little if it excludes planning, cabinetry production, benchtop fabrication or final fit-off.

Plan the Timeline Before Choosing the Start Date

Bluestone Build Co. is best suited to kitchen-led renovations where the laundry, pantry, flooring, lighting or connected finishes form part of the overall project.

Our Renovation Plan costs $500 + GST. It establishes the project direction, scope, sequence, likely programme and major cost drivers before construction dates are promised.

You keep the plan whether or not you proceed with Bluestone. If you engage us to deliver the renovation, the fee is credited back in full.

Send Your Project Details

Continue Planning

Previous
Previous

Top Bathroom Design Trends for 2025: What Melbourne Homeowners Are Choosing Now

Next
Next

Modular Kitchen Designs vs Custom Renovations: What Melbourne Homeowners Should Know