How to Plan a Kitchen Renovation in the Right Order

Plan a Melbourne kitchen renovation in the right order: brief, site constraints, budget, layout, appliances, specifications, approvals and construction.

Read the guide
In this guide01 / 13

A kitchen renovation becomes difficult when decisions are made in the wrong order.

Choosing cabinet colours before the layout, buying appliances before checking services or accepting a price before the specification is complete creates rework and uncertainty.

Use a sequence that moves from the household’s needs to the site, design, specification and construction.

1. Write a brief from daily problems

Start with what the current kitchen fails to do.

  • Where do people collide?

  • Which appliance doors block the room?

  • Where does food preparation happen?

  • What stays on the bench because it has no home?

  • Who cooks, unloads, packs lunches or supervises children?

  • How does the kitchen connect to dining, living and outdoors?

Separate needs from preferences. “A clear preparation bench beside the sink” is a need. “A three-metre island” is one possible solution and should not be fixed before the room is tested.

2. Measure the site and investigate constraints

Record room dimensions, ceiling heights, windows, doors, floor levels, structural walls and existing services. Open cupboards and inspect accessible areas rather than assuming the walls and floor are straightforward.

Older homes can contain undocumented changes, uneven surfaces or services in unexpected positions. Not every condition can be known before demolition, but a proper site review reduces avoidable surprises.

If the kitchen is part of a wider alteration, confirm whether structural work, planning permission or a building permit may be required. Consumer Affairs Victoria says the owner must make sure required planning and building permits are obtained, even when an agent handles the process.

3. Set a scope-based budget

A useful budget reflects the proposed work, not a generic kitchen price.

Include:

  • design, documentation and approvals where required

  • demolition and waste

  • cabinetry, benchtops and splashback

  • appliances and fixtures

  • plumbing, electrical, gas and ventilation

  • flooring, plastering and painting

  • structural or window changes

  • temporary kitchen arrangements

  • a contingency appropriate to the known and unknown conditions

Do not use one arbitrary percentage as proof that the contingency is sufficient. The amount should reflect how complete the documentation is and what remains concealed.

4. Test layout options before styling

Draw at least two credible layouts. Show appliance doors, drawers, stools and normal walking routes at scale.

Compare each option for preparation space, circulation, storage, daylight, extraction and service changes. An island, pantry or relocated sink may look attractive while making the construction more expensive or the room less efficient.

Use the guides to open and closed layouts and kitchen islands as tests, not formulas.

5. Select appliances before final cabinetry

Cabinet openings, ventilation gaps, door clearances, power, water and drainage depend on exact models.

Record each model number and installation document. Check:

  • overall and cut-out dimensions

  • hinge and handle projection

  • required ventilation and clearances

  • electrical load or gas requirements

  • water and drainage connections

  • service and removal access

For gas cooking, Energy Safe Victoria says new installations and kitchens renovated with new cupboards must follow current overhead-clearance requirements and any greater clearance specified by the appliance or rangehood manufacturer. The licensed trades must confirm the installation.

6. Build a storage inventory

List food, cookware, plates, containers, appliances, bins and occasional items. Assign everyday items to the easiest locations and keep heavy items where they can be handled safely.

This shows whether the kitchen needs a walk-in pantry, tall cabinets, wide drawers or simply better internals. It also prevents storage from consuming all available bench space.

Work through the kitchen storage planning guide before finalising joinery.

7. Coordinate services and ventilation

Resolve sink, dishwasher, refrigerator, cooking, rangehood, power points and lighting as one plan.

Confirm how the rangehood discharges, where ducts pass through the building and how they are accessed. The National Construction Code includes kitchen ventilation provisions; appliance instructions and the applicable building requirements must be coordinated.

Plan power for benchtop appliances, charging and any island without putting outlets where cords cross water, heat or circulation. Licensed trades should confirm the final design.

8. Write the specification

A drawing shows where something goes. The specification states what it is.

Record:

  • cabinet substrate, finish, edge and hardware

  • benchtop product, thickness, edge, joins and support

  • splashback material and extent

  • appliance and fixture model numbers

  • flooring, paint and lighting

  • allowances, exclusions and responsibilities

Consumer Affairs Victoria advises putting everything wanted into the plans and specifications before signing because later changes can be expensive and may require a permit amendment.

9. Compare like with like

A lower total is not automatically better value if it omits demolition, trades, painting, flooring, permits or a defined product specification.

Compare each proposal against the same drawings and written scope. Identify provisional sums, prime-cost items, exclusions and assumptions. Ask how changes and concealed conditions will be documented and priced.

A quote that cannot be traced back to a clear scope is difficult to assess and difficult to administer.

10. Plan decisions and construction

Build the program around approvals, product lead times, site preparation and trade sequence. Confirm when the kitchen becomes unusable and how the household will manage food, water, refrigeration and washing up.

A programme is not a guarantee that every hidden condition or supplier delay disappears. It should show dependencies, decision deadlines and who is responsible for each item.

Before signing or ordering

  1. The brief and scope agree.

  2. The site has been measured and key constraints investigated.

  3. The layout works with doors, drawers and people.

  4. Exact appliances and fixtures are recorded.

  5. Services, extraction and lighting are coordinated.

  6. Materials and finishes are specified, not described vaguely.

  7. Permit responsibilities are clear.

  8. Price allowances, exclusions and variation process are understood.

  9. Lead times and temporary-kitchen arrangements are planned.

Where Bluestone fits

Bluestone coordinates design and construction so the layout, products, trades, approvals and programme are resolved as one renovation rather than separate purchases.

See Bluestone’s approach to complete kitchen renovations in Melbourne.

Official sources used

What would you change
in your kitchen?

Tell us what isn’t working, your suburb and a rough budget. We’ll get in touch to discuss your kitchen.

Discuss my kitchenNo finished plans needed.
View the full Journal
Bluestone Build Co.
01 / 02Your renovation → Your details

Your renovation.

Which rooms? Choose any.
Total renovation budget

A rough idea is fine.

Anything you’d like us to know? Optional
Use the full-page form

Your details are only used for your enquiry.

Privacy choices

Choose what helps Bluestone improve.

These settings control optional website measurement. Essential security and form functions still work.

Checking the privacy default for this visit.

You can change these choices at any time from the footer. Read the privacy policy.